Key takeaway
Key takeaways
- Exact models, not categories, on the equipment list
- Spares for anything that would stop the show
- Power sanction plus generator changeover confirmed
- One named show-caller holding the cue sheet
Event Production: pre-show checklist
Equipment & specification
- Contract structure confirmed: One technical contract spanning sound, video, lighting, staging, rigging and crew
- Document set confirmed: Technical drawing, rigging load plan, power plan, cable schedule, build programme, run of show
- Drawing standard confirmed: Scaled plan and section in AutoCAD or Vectorworks, revision-numbered and issued
- Recce output confirmed: Measured survey of rigging points and capacities, power positions, dock, lift and trim heights
- Comms confirmed: Clear-Com or Riedel partyline with separate production, lighting and stage rings
- Itemised list naming exact models, not categories
- Spares for mics, cables, processors and any single point of failure
Power & safety
- Venue sanctioned load confirmed in writing against the rig's draw
- Silent generator sized with automatic changeover
- Earthing check completed and logged
- Rigging certification and load calculations signed off
- Cable covers on every walkway and crowd line
People
- Producer named and briefed
- Production manager named and briefed
- Show-caller named and briefed
- Department heads named and briefed
- Rigging lead named and briefed
- Stage manager named and briefed
Timings
- Load-in slot agreed with the venue in writing
- Sound check and line check scheduled
- Full technical rehearsal booked with real presenters and real content
- Venue curfew and strike window confirmed
Content & handover
- Scope document naming what each department owns and where the interfaces sit
- Measured recce report with rigging capacities, power positions and access dimensions
- Scaled technical drawing in plan and section, revision-numbered
- Rigging load plan with calculated point loads and venue sign-off
- All video, audio and slides delivered 72 hours ahead in the agreed format
What this checklist is protecting you from
What can go wrong
How we prevent it
- What can go wrong
Four vendors each deliver their own scope and nobody owns power distribution, so the LED wall and the lighting rig end up sharing an overloaded phase.
How we prevent itOne power plan with a per-phase load schedule is drawn before anything is ordered, and a single electrical contractor feeds every department from distribution we specify and label.
- What can go wrong
The stage build overruns, lighting loses its focus window, and the show opens with an unfocused rig.
How we prevent itThe build programme gives each department a named slot with float, and the production manager holds a documented decision point at which stage scope is reduced rather than allowed to consume the next department's time.
- What can go wrong
The venue refuses a rigging point on build day because no load plan was ever signed off.
How we prevent itPoint loads are calculated against the venue's own structural capacity and approved at drawing issue, with a ground-support fallback carried in the design for any point the venue will not confirm.
- What can go wrong
The agency reorders the running order the evening before and three departments hear about it separately.
How we prevent itThe run of show has one owner and one revision number, changes are reissued to the whole distribution list, and the show-caller calls only what is in the current revision.
- What can go wrong
Decor arrives and occupies the control position and the loudspeaker positions agreed in the drawing.
How we prevent itAn interface schedule is agreed with the decorator at drawing stage, positions are marked on the floor before either team unpacks, and the production manager walks the site with the decor lead at the start of build.
- What can go wrong
A console or playback machine fails mid-show and there is no plan, because redundancy had been treated as an optional extra.
How we prevent itRedundancy sits inside the design scope — tracking backup console, mirrored playback, duplicated encoder, second comms ring — and the failover is proved at rehearsal by deliberately killing the primary.