Key takeaway
Key takeaways
- Single booth
- Feature stand
- Pavilion plus keynote
- Hall-wide production
What exhibitions & trade shows budgets actually cover
An exhibition is a power-distribution problem before it is an audio-visual one. Every booth draws from a shared hall supply through a metered feed ordered weeks in advance from the organiser's appointed electrical contractor, and the single most common cause of a dark booth is a feed ordered at half the load the LED wall and processing actually need. Calculate the draw honestly, order single or three phase deliberately, keep LED processors and media players on their own circuit away from switched lighting, and put a small uninterruptible supply behind anything whose reboot takes four minutes.
Scope levels
A 3x3 or 4x4 metre stand for three days: an LED wall or large-format screen, a media player with attract-loop playback, a touchscreen and a short-throw audio point.
A larger pavilion with multiple screens or a shaped LED feature, interactive stations, accent lighting, local content management and a technician attending daily.
A hall pavilion with a presentation stage: PA, delegate and radio mics, presentation switching, session recording, and multiple booth screens on a managed content system.
Organiser-side delivery across a full hall: inaugural stage, registration and wayfinding screens, pavilion lighting, multiple session rooms and a floating crew for the run of the show.
Where scope quietly expands
What can go wrong
How we prevent it
- What can go wrong
The booth trips and takes a section of the hall's phase with it.
How we prevent itCalculate draw per circuit honestly, order the correct feed from the appointed contractor, balance across phases, and put inrush-heavy LED and lighting on separate protected circuits with their own breakers.
- What can go wrong
The power order is placed at half the real load to save money.
How we prevent itProduce a written load schedule per device at design stage, size the order to measured draw plus headroom, and treat the contractor's feed cost as fixed infrastructure rather than a negotiable line.
- What can go wrong
Content arrives in the wrong aspect for a non-standard LED canvas.
How we prevent itIssue the exact pixel canvas map and safe area to the content team at briefing, and test the real files on the real processing during the build rather than on a laptop.
- What can go wrong
The truck sits in the marshalling queue and the build window shrinks.
How we prevent itBook a load-in slot, load in build order with numbered cases, and send a small advance team to secure the footprint while the vehicle waits its turn.
Typical split
Roughly a third sound, a third screens and video, a quarter lighting and staging, and the remainder crew, transport and power. Your scope: booth LED & touchscreens; keynote stage PA; pavilion lighting; content playback. Get an itemised quote from Prime AV Solutions within 24 hours — call +91 93093 80958 or WhatsApp our producers.
Published 2 December 2025 by the Prime AV Solutions production team.